<br />WORK CURRENTLY IN PROGRESS AND PARTIALLY COMPLETED: <br />1. ROAD SIDE DAMAGES: <br />a. Area #4 is nearly completed (only some additional grading, <br />shaping, and topsoiling is needed, but it can only be done with <br />specialized rental equipment that is currently unavailable). <br />~nan~nn~c+rn~~au~nn~~~nn~~~+~uuxauuncnnnn~nnnncarn~~nnnuanunnn~nn <br />CORRECTIVE ACTIONS THAT HAVE NOT BEEN COMPLETED: <br />1. WILLIAMS CANYON: <br />a. Trees have yet to be planted and monitoring system established. <br />2. ROAD SIDE DAMAGES: <br />a. Areas #2 and #3 have yet to be graded, topsoiled, seeded, s.nd <br />planted with trees. <br />3. SILT RETENTION FACILITY: <br />a. Needs to be constructed. <br />4, CULVERTS: <br />a. HR6 needs to be installed once a decision is made as to what <br />option will be implemented. There are currently 11 options. <br />b. As built drawings need to be completed. <br />5. ROCKFALL HAZARD: <br />s. System established for Phase II prior to mining on canyon side <br />of ridgeline crest (current estimated need date is 1994). <br />6. MONITORING PROGRAM <br />a. Implementation of the monitoring program awaits completion of <br />the tree plantings. Reports will begin with the 1991 annusl <br />report (due May 27, 1991). <br />Page 3 of 7 SNYDER CAP UPDATE 6-27-90 <br />