My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2002-10-01_REVISION - M1998013
DRMS
>
Day Forward
>
Revision
>
Minerals
>
M1998013
>
2002-10-01_REVISION - M1998013
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
6/15/2021 2:13:56 PM
Creation date
11/21/2007 11:03:52 AM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1998013
IBM Index Class Name
Revision
Doc Date
10/1/2002
Doc Name
Amendment Application
From
Hall-Irwin Corporation
To
DMG
Type & Sequence
AM1
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
36
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
The Shores Resource -Amendment No. 1 <br />Table for Reclamation Cost Estimate <br />Activity Quantity Units Unit Costs Cost <br />A. Phase 8 - 95% mined -approximately 59 acres of <br />disturbance. Fill sideslopes of pond with overburden <br />material and shape, seed and mulch shoreline - <br />approximately 6420 linear feet perimeter distance at <br />limit of mining <br />I Replace fill material using overburden and shape pond <br />side slopes at 3: l 201,160 CY $ 1.25 $ 2S 1,450.00 <br />2 Replace overburden and shape the shoreline @ 4:l 7,609 CY $ 1.25 $ 9,511.11 <br />3 Replace 12" of topsoil on the shoreline @ 4:1 4,903 CY $ L2S $ 6, t 28.72 <br />4 Seed and mulch shoreline 3.0 Acres $ 800.00 $ 2,431.23 <br />' ,bs~'c-~~ ..'bfoha°1; ~$u?£~?~~,'2#1~'4~ <br />B. Dewatering trench would be excavated to nearly the <br />and bottom elevation and fill with water --- ----- ---- ----- <br />_ ~ s „ _ <br />C. Phase 7 -Would be 100% reclaimed _____ _____ _____ _____ <br /> ~. <br />D. Processing area. Processing equipment is portable and <br />would be removed by the operator <br />1 Move serge piles into settling pond 1,000 CY $ 1.25 $ I,2S0.00 <br />2 Remove concrete pad for wash plant 1 S CY $ 65.00 $ 975.00 <br />3 Remove concrete pad for asphalt plant 60 CY $ 65.00 $ 3,900.00 <br />4 Remove concrete pad for concrete plant 37 CY $ 65.00 $ 2,405.00 <br />5 Demolish and remove shop 1 LS $ 2,000.00 $ 2,000.00 <br />6 Remove concrete footings for office 8 CY $ 65.00 $ 520.00 <br />7 Remove concrete base for scale 10 CY $ 65.00 $ 650.00 <br />8 Scarify ground 2S Acres $ iS0.00 $ 3,750.00 <br />9 Spread l2" topsoil 8,067 CY $ 1.25 $ 10,083.33 <br />10 Seed and Mulch 2S Acres $ 800.00 $ 20,000.00 <br />~ w,,. ,~ <br />;i~tikc.~.•.. ~, .. .. <br />SUUt6tal <br />$:$5.~5~„ . <br />E. Settling Ponds <br />1 Place 12" overburden on 0.25 acre 403 CY $ I.25 $ 504.17 <br />2 Place l2" topsoil on 0.25 acre 403 CY $ 1.25 $ 504.17 <br />3 Seed and Mulch 0.25 Acres $ 800.00 $ 200.00 <br />~rzx'a' " $ithtotal '$ ~+208~3~3, <br />Total Disturbance Costs $ 316,262.73 <br />Contracror Mobilization (8%) $ 25,301.02 <br />Overhead(iB.S%) $ S8,S08.60 <br />Admnustration (S%) $ 15,813.14 <br />Total $ 41S,88S.49 <br />HALL-IRWIN CORPORATION -THE SHORES AMENDMENT I (#M-1998-013) Page 22 of 29 <br />
The URL can be used to link to this page
Your browser does not support the video tag.