Laserfiche WebLink
EXHIBIT L: Reclamation Cost Estimate <br />RAINDANCE RESERVOIR (East Pit) <br />Item Quantity Cost Total <br />Overburden replacement/backfill' 66,200 yds3 $0.40 yd3 $26,480 <br />Topsoil Replacement 29,750 yds3 $0.40 yd3 $11,900 <br />Grading Stockpile & Plant Site2 (If no <br />surcharge reservoir) 6.0 acres $200 /acre $1,200 <br />Seeding -reservoir cut slopes 3.3 acres $400 /acre $1,320 <br />Seeding-Stockpile & Plant site2 (If no <br />surcharge reservoir) 6.0 acres $400 /acre $2,400 <br />Pond Dewatering 600 ac-ft $60/ac-ft $36,000 <br />Clay Liner Excavation, Placement, <br />Conditioning and Compaction 161,300 yds3 $1.00 /yd3 $161,300 <br />Construction QA/OC _ 1 ~ $25,000 $25,000 <br />Mobilization/Demobilization 1 $20,000 $20,000 <br />Direct Cost $285,600 <br />Insurance, Performance Bond and Protit <br />(15%) $41,840 <br />Total Cost $328,440 <br />SURCHARGE RESERVOIR (West Pit) <br />Item quantity Cost Total <br />Overburden replacemenl/backfill' 154,650 yds3 $0.40 yd3 $61,860 <br />Topsoil Replacement 9,700 yds3 $0.40 yd3 $3,880 <br />Grading Stockpile & Plant Site2 (It surcharge <br />reservoir is constructed) 6 acres $200 /acre $1,200 <br />Seeding -reservoir cut slopes and fill areas 8.6 acres $400 /acre $3,440 <br />Seeding-Stockpile & Plant site2 (If surcharge <br />reservoir is constructed) 6.0 acres $400 /acre $2,400 <br />Pond Dewatering 100 ac-ft $60/ac-ft $6,000 <br />Clay Liner Excavation, Placement, <br />Conditioning and Compaction 0 yds3 $1.00 /yd3 $0 <br />Construction QA/OC 1 $15,000 $15,000 <br />Mobilization/Demobilization' <br />Direct Cost $93,780 <br />Insurance, Performance Bond and Profit <br />(15%) $14,067 <br />Total Cost $107,847 <br />1. The overburden total is less the volume to be used for haul road and plant site construction. <br />2. The re-grading and re-seeding of the stockpile locations and the plant site location shall occur only once, and <br />is a function of the surcharge reservoir construction. <br />3. If surcharge reservoir is constructed there will not be a mobilization fee as equipment will already be on-site. <br />The demobilization fee shall only occur once and that fee was included in Raindance Reservoir cost. <br />