• The table below describes the time sequence of the mining within the NH2 permit area. <br />TABLE 2.05.3-1 -TIMING OF OPERATIONS <br />• I <br />• l <br />ITEM DESCRIPTION DATE <br />1 Install Enstrom, Wilcox, Johnson access road from Morgan road Start 2003 <br />2 Mine through 2700 Road going west. Mid 2003 <br />3 Place 2700 Road and BB Road in original locations as a gravel surface. <br />Continue using detour. Restore West Lateral Ditch in permanent <br />pipeline location. Mid 2008 <br />4 Pave 2700 Road and BB Road in original locations and restore <br />Sunshine Ranch Corner intersection. Also lay power and phone lines in <br />original locations. Mid 2008 <br />5 Remove BB Road detour and reclaim road area End 2008 <br />6 Mine west to last cut at western permit boundary End 2010 <br />7 Backfill final cut with overburden stockpile Mid 2011 <br />8 Re-topsoil and re-vegetate final cut area End 2011 <br />9 Replace BB Road from Sunshine Ranch Corner to westem boundary. <br />Iso re-install power lines and phone lines along road. End 2011 <br />10 Continue to irrigate and monitor reclaimed areas until final bond <br />release. Many areas will be given back to the original owners, <br />especially irrigated areas, much earlier than the date shown here. Start 2022 <br />Items 1,2 and 3 have been done as of the Mid Term Review of 2006. Item 4 is scheduled for <br />completion as previously described in 2008. <br />(REVISED MARCH 2006) 2.05.3-8 <br />