<br /> <br />Memo to Gregg Souire 2 Julv 2 2001 <br />Slurry Wall: <br />The direct cost [o be incorporated into the reclamation bond relative to the proposed slurry wall is estimated <br />as follows. <br />Given: Perimeter of Area C = 3200 linear feet. <br />Average depth to shale = 34 feet. <br />Average depth of slurry wall = 34 f[. + 3 ft. (keyway) = 37 ft. <br />3200 ft. x 37 ft. $3.00/sq.ft. x 20 percent = $71,040. <br />Quality Assurance: <br />The clay liner installation around 2200 linear feet of pil perimeter at the north end of Area B is estimated to <br />require 205 hours of earthwork, or approximately 26 days (see attached estimating worksheets). Quality <br />assurance testing, observation, and report preparation at $500.00 per day for 30 days yields a cost of <br />$15,000.00 for the project. <br />Summary of Direct Costs: <br />The Applicant is eligible for the 20 percent bonding option under the "Slurry Wall and Clay Liner Guide." <br />As a result, the direct pit lining and slurry wall installation costs to be included into the bond are: <br />Dewaterin $65,000.00 <br />Borrow (ri )liner fill $30.458.00 <br />Install cla liner $147,627.00 <br />Slu wall $71,040.00 <br />Qualit assurance $15.000.00 <br />Total $324,125.00 <br />This analysis does not consider other direct reclamation casts, such as topsoiling and revegetation, nor does it <br />consider the indirect costs. <br />Reporting Requirements: <br />The Operator should be required to provide the construction quality assurance (CQA) report and engineers <br />certification within 60 to 90 days after the completion of the slurry wall. The Operator should further be <br />required to supply a discussion of clay liner installation progress with each annual reclamation report, and a <br />summary of ongoing CQA results for [he clay liner. <br />attachment(s) <br />cc: Carl Mount, DMG (w/o «u«clunents & via electronic tr«nsmrssion) <br />e:\wi ndows\pers~n alVohmnnn. dac <br />