2. Reclamation Timetable <br />The time for reclamation is shown below. Exhibit L: Reclamation Costs describes the worst case <br />bond scenario. <br />Table E-2 <br />Task # Description Time Needed Months <br />1 Prepare sediment pond and collection <br />ditches. 0.5 <br />2 Strip topsoil from Staging Area and Phase <br />1. Strip overburden from Phase 1. Store <br />topsoil and overburden in separate <br />stoc files. 0.5 <br />3 Mine Phase 1. 40.7 <br />4 Reclaim Phase 1 and mine Phase 2. 36.8 <br />5 Reclaim Phase 2 and mine Phase 3. 35.0 <br />6 Reclaim Phase 3 and mine Phase 4. 32.1 <br />7 Reclaim Phase 4 and mine Phase 5. 38.1 <br />8 Reclaim Phase 5 and mine Phase 6. 35.3 <br />9 Reclaim Phase 6 and mine Phase 7. 38.8 <br />10 Reclaim Phase 7 and mine Phase 8. 40.4 <br />I 1 Reclaim Phase 8 and mine Phase 9. 33.0 <br />12 Reclaim Phase 9 and mine Phase 10. 31.1 <br />13 Reclaim Phase 10 and mine Phase 11. 34.3 <br />14 Reclaim Phase 11 and mine Phase 12. 36.9 <br />15 Reclaim Phase 12 and Staging Area. 3.0 <br /> Total months 437 <br /> Total years 36.4 <br />3. Reveeetation Plan <br />For both the dryland and wetland azeas, the soil will be disced loosen the soil. Due to the mild <br />grade, seed can be drilled in both regions. The dryland areas will be seeded with the NRCS <br />recommended seed mix. Certified weed free mulch will be crimped into the surface at 2000 lbs <br />per acre. The wetlands will be seeded with a specially designed mix. Fertilizer maybe added as <br />Anderson Pi[ February OS E-3 <br />