My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
PERMFILE51440
DRMS
>
Back File Migration
>
Permit File
>
600000
>
PERMFILE51440
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 10:55:31 PM
Creation date
11/20/2007 2:54:21 PM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
Permit File
Doc Date
9/3/2002
Doc Name
Certification Report-Summary Report No. 53
From
Cripple Creek & Victor Gold
To
DMG
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
39
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Golder observed and tested placement of SLF in Phase Na, completing thirty in-situ density tests, <br />fifteen depth verification tests, and verified surface prepazation. Prior to geomembrane deployment, <br />the SLF met the requirements of the specifications. <br />Golder observed anchor trench excavation for proper location and dimension (2' wide and 3' deep). <br />Anchor trench excavation met or exceeded the requirements of the specifications. <br />Golder observed geomembrane deployment, documenting ambient air temperature, panel <br />dimensions, seaming, tie-in overlap, and seam testing (trial seams, pressure, vacuum, and <br />destructive). Geomembrane placed in the Phase IVa area met the project specifications. <br />Golder observed construction of the Primary and Secondary Underdrains in Phase Nb for trench <br />dimensions (5' by 3' and 4' by 2'), slope (minimum 1%), materials, and geotextile overlap. <br />Golder observed and documented excavation and remediation activities associated with the Phase IV <br />underground working construction. <br />Golder observed and documented confirmation drilling activities associated with the Phase IV <br />construction. Full-time monitoring was given to confirmation drilling of underground workings, <br />including logging holes, mazking drill locations, surveying holes, and documenting underground <br />workings encountered. <br />Golder visually observed the placement of DCF in the Phase IVa azea. Golder had one CQA monitor <br />per dozer to observe DCF placement. <br />Laboratory Tests <br />Golder obtained four samples of SLF (SLFa-08 through SLFa-11) for laboratory testing. The <br />samples tested met the requirements of the specifications and results are presented in Attachment B. <br />Meetin¢s <br />CC&V held a Weekly Contractors meetings on July 16ei and July 23`d. Items discussed included <br />Safety, Environmental, Schedule, and CQA. The next weekly meeting will be held on July 30~', <br />2002 at 10:00 AM. <br />Golder Personnel On-Site <br />A summary of all Golder CQA personnel on site during this reporting period is presented in <br />Attachment C. <br />I• PIwe1Ve59lulyl43].doc GOIderAS50cidteSlnC. <br />