<br />EXHIBIT -D <br />MINING PLAN <br />Seahorse Ranch West Gravel Pit. Prior to mining operation start up, the entire mine site is to be fenced <br />with a four wtre (barbless wire) fence. The mining plan for this site consists of a two-stage program. The <br />pit site is divided in to two sections by a road, shown on map as "Old Railroad Grade". This road runs east <br />to west through the noM portion of the site and is the entrance road to the site. <br />First Stage: <br />The first stage of the mining program includes an area just to the north of the road and a staging azea just to <br />the south of the road. The mined area is the site be[wern the road and south of the Tomichi Creek. The <br />mining operation includes a process that is designed to reclaim the area as the excavation process takes <br />place. The topsoil is to be removed and is to be stored with in the creek and site boundary set back <br />locations. The perimeter of the minded area is to be excavated, placing the pit run material in to the center <br />of the mined area. The excavation of the perimeter is to be completed using a 3:1 slope to a depth of 10 <br />feet. As the excavation process continues below the IO-foot depth, a 2:1 slope is to be mined until the <br />bottom of the mined area is reached. The excavation process is to continue, as pit run material is required. <br />Pit run material is to be stored in the center of the mined area and removed, as it is requved. At a point <br />where the 10-foot depth perimeter is fully mined, the topsoil will be reset in to the perimeter area, and the <br />called for seeding and planting is to be completed, thus reclaiming the perimeter areas. <br />At a location just to the north of the road and at the east end of the mined site a Wash Plant is to be <br />installed. The Wash Plant is to remain at this location for the entire life of the gravel pit operation. Just to <br />the south of the road, running from the entrance bridge (west end) to the east end of the mined site, a <br />staging area is to be constructed. The staging area is approximately 6 acres in size. This area is to be used <br />to stage processed materials, crushing plants, asphalt plants and other equipment required for mining, <br />excavation and material processing. <br />Second Stage: <br />The second stage is located just to the south and west of the road. Griffin Ditch # 1 runs east to west <br />through a portion of the area and is to be relocated around the south perimeter of the mined area. Mining of <br />the area is to be completed using the same mining method employed in the "Fvst Stage" mined area. <br />Topsoil is to be removed and stored in the set back areas. 77re area perimeter is to be excavated to a depth <br />of ] 0 feet at a 3:1 slope. Pit run material is to be stored in the center of the mined area and removed as <br />needed. As the perimeter is fully mined the topsoil is to be reset in to the perimeter area, and as called for <br />seeding and planting is to be completed. Below the 10 foot depth excavation is to take place at a 2:1 slope <br />until the bottom of the mined area is reached Pit run material is to be stored in the center of the mined azea <br />and removed as needed. <br />The staging area just to the south of the road is to be excavated as the final stage of the mining process. <br />This area is to be excavated using a 3:1 slope until it reaches the already mined areas. Pit run material is to <br />be removed from the site and processed elsewhere. <br />