Page 1 of 1 • <br />EXHIBIT L <br />RECLAMATION COSTS <br /> <br />These reclamation costs assume that all stockpiles are removed from <br />the pit floor. The side slopes are set at no steeper than 3H to 1 V during <br />the mining operation. Once the toe of the pit wall has reached its point <br />the slope is shaped accordingly. Please see the areas marked on the <br />reclamation cost map for a better understanding of the finished area. <br />Topsoil will only be required in area shown. The balance of the side <br />slopes will have had topsoil applied. <br />Listed is a table of the oroiected reclamation costs for Phase 1. <br />ITEM DESCRIPTION QUANTITY UNIT UNIT AMOUNT <br />NO. RATE <br />1 RIP PIT FLOOR FOR 16.05 ACRE $150.00 <br /> COMPACTION $2,407.50 <br />2 SPREAD TOPSOIL 3" 16.OS ACRE <br /> THICK ON SLOPES AND <br />PIT FLOOR 6475 CUBIC <br />$1.50 <br />$ 9,712.50 <br /> (AVG HAUL < 700 LF) YD <br />3 SEEDING 16.05 ACRE $500.00 $ 8,025.00 <br /> <br /> SUBTOTAL $20,145.00 <br /> ADD PROFIT 8 10% $2,014.50 <br /> OVERHEAD <br /> TOTAL $22,159.50 <br />Listed is a table of the Droiected reclamation costs for Phase 2 <br />ITEM DESCRIPTION QUANTITY UNIT UNIT AMOUNT <br />NO. RATE <br />1 RIP PIT FLOOR FOR 14.50 ACRE $150.00 <br /> COMPACTION $2,175.00 <br />2 SPREAD TOPSOIL 3' 14.SO ACRE <br /> THICK ON SLOPES AND <br />PIT FLOOR <br />5848 <br />CUBIC <br />$1.50 <br />$ 8,772.00 <br /> (AVG HAUL < 700 LF) YD <br />3 SEEDING 14.50 ACRE $500.00 $ 7,250.00 <br /> <br /> SUBTOTAL $18,197.00 <br /> ADD PROFIT & 10% $1,819.70 <br /> OVERHEAD <br /> TOTAL $20,016.70 <br />