Renner <br />• Page 2 <br />January 30, 1987 <br />Since the overburden from the temporary scraper area will <br />be backfilled into the north-south Wadge Pit, there will <br />be no increase in open pit resulting from this revision. <br />Thus, worst-case bond calculations as presented in the <br />permit renewal are still valid and this revision should <br />require no increase in bond. <br />When the 7708 has been put back in service, it will <br />commence operations from the point it went down and pit <br />progression will proceed in accordance with the approved <br />plan. <br />Because of the emergency nature of this request, PCC is at <br />your disposal to answer any questions you might have in <br />order to expedite this minor revision process. <br />Thank you for your consideration. <br />• <br />sj <br />encl. <br />Sincerely, , <br />% James 5. Lurian <br />hlanayer - Permits <br />C~ <br />