• i <br />• Phase 3 Area B2 will be quarried for limestone. The available topsoil <br />from Area B3 will be removed and stockpiled in the designated <br />area and preserved. The overburden from Area B3 will be <br />blasted, hauled and stockpiled in area B1. The overburden <br />varies in depth from 0 to 20 feet thick, averaging 10 feet. <br />The overburden will be backfilled on an average of 20 feet <br />thick in Area B1. <br />The high calcium limestone will be removed from area B2 using <br />conventional open pit drilling and blasting methods. The <br />limestone will be loaded into trucks and hauled to the stock- <br />pile area for sizing and stockpiling. <br />This phase will require approximately 36 months and the disc_.. <br />turbance will be approximately: <br />Major - 3.U acres <br />Moderate - 1.50 acres <br />Minor - 0 <br />• <br />• <br />