Minor Revision 258 -MR-258 proposed disturbance for a light-use road along the west side of
<br /> Taylor Creek. The revision was received on August 15, 2024, deemed complete on August 15,
<br /> 2024 and approved on August 16, 2024. +$8,710.00
<br /> Minor Revision 259 -MR-259 proposed to retain the Streeter Pond as a permanent impoundment
<br /> at the request of the surface landowner. The revision was received on August 21, 2024,
<br /> deemed complete on August 26, 2024 and approved on August 28, 2024.
<br /> Technical Revision 164 - TR164 provides the as-built for the Upper and Lower Section 3 Ponds.
<br /> The revision was received on September 19, 2024, deemed complete on September 20, 2024
<br /> and approved on November 1, 2024.
<br /> Technical Revision 165 - TR165 proposed reduction of the permit boundary to remove the
<br /> Streeter Ditch and Pond. The revision was received on December 12, 2024, deemed complete
<br /> on December 20, 2024 and approved on March 3, 2025.
<br /> Technical Revision 166 - TR166 proposes changes to the Colowyo's topsoil replacement and
<br /> seeding plans. The revision was received on March 11, 2025, deemed complete on March 12,
<br /> 2025 and approved on April 8, 2025.
<br /> Minor Revision 260 -MR-260 provides an updated certificate of liability insurance for Colowyo.
<br /> The revision was received on April 8, 2025, deemed complete on April 8, 2025 and approved on
<br /> April 8, 2025.
<br /> Minor Revision 261 -MR-261 updates the permit by removing references to Streeter Pond and the
<br /> lower segment of Streeter Ditch which have been Phase III released and are now outside the
<br /> mine permit boundary. The revision was received on April 9, 2025, deemed complete on April
<br /> 9, 2025, and approved on April 9, 2025.
<br /> Minor Revision 262 -MR-262 updates the permit by proposing to retain the Streeter South Side
<br /> Ditch as a permanent structure. The revision was received on May 5, 2025, deemed complete
<br /> on May 9, 2025, and approved on May 19, 2025.
<br /> Minor Revision 263 -MR-263 updates the permit by proposing a test pilot plant for the East
<br /> Taylor Spring. The revision was received on May 7, 2025, deemed complete on May 9, 2025,
<br /> and approved on May 19, 2025. +$4,057.00
<br /> Minor Revision 264 -MR-264 updates the permit by providing responses to the Division's
<br /> midterm 9 (MT-9)review. The revision was received on June 9, 2025, deemed complete on
<br /> June 18, 2025, and approved on June 30, 2025. +$14,681,203.00
<br /> Technical Revision 167 - TR167 updates the permit by proposing to reduce the permit boundary to
<br /> remove Phase III areas applied for bond release under SL-24.The revision was received on
<br /> July 14, 2025, deemed complete on July 24, 2025 and approved on September 9, 2025.