Laserfiche WebLink
Exhibit L Reclamation Costs <br /> Volumes / Areas <br /> 38.77 acres to be reclaimed, plus access road from scales into mine area <br /> Unit Costs <br /> topsoil placement with scraper $1.45 per cu yd <br /> blade per hour $125.00 per hour <br /> equipment trips from Greeley $400.00 per round trip <br /> service/fuel truck $500.00 per day <br /> dozer per hour $100.00 per hour <br /> Direct Costs <br /> Final Grading <br /> 60 hrs blade time $7,500 <br /> 12000 cu yds of overburden placed $17,400 <br /> 32000 cu yds of topsoil placed $46,400 <br /> 3 equipment trips $1,200 <br /> 6 service/fuel truck days $3,000 <br /> 40 hrs dozer time $4,000.00 <br /> scale removal 5,000 <br /> Total Direct Costs $84,500 <br /> Indirect Costs <br /> Insurance/Bond/Superintendant/Profit @ 18% $15,210 <br /> Legal/ Engineering/Project Management @ 14% $11,830 <br /> Contingency $0 <br /> Total Indirect Costs $27,040 <br /> Total Reclamation Cost $111,540 <br />