Natural Soda LLC 2024 Project Status Report & Annual Plan of Development <br /> 15 January 2025 <br /> <br />4.1.4. Wells Associated with the NS Project (Confidential) <br />The following well-field related activities occurred in 2024: Refer Figure 3 & Figure 4 Plant <br />and Well Location Map. <br />• The 89-2 A-Groove groundwater monitoring well sampling equipment was <br />experiencing difficulties during sampling events in late 2023. NS removed the <br />nitrogen lift pump (NLP) and tubing on February 20, 2024. The NLP and tubing <br />were replaced with new components and the equipment was tested for proper <br />post installation operations. <br />• On May 1st, construction of a cuttings pit for the 18H drilling operations <br />commenced on the 18H-1V pad. Additional location preparation for 18H-1V <br />and 18H-IR-W drilling operations continued the first two weeks of May 2024. <br />• A new production well, the 18H-1V Slant Well, was spudded on May 15th with <br />the Capstar Drilling Rig #321. The 18H-1V production well was drilled and <br />completed to its final total depth on May 26, 2024. <br />• The 18H-IR-WA production well was spudded on May 29th, 2024. Drilling <br />operations ceased on June 19th in 18H-IR-WA production well, due to cement <br />plug and casing damage issues. All equipment was rigged down and <br />demobilized from the location. The NS 18H-IR-WA well was Plugged and <br />Abandoned (P&A) July 15th through July 18th, 2024. The 9 5/8” casing was <br />perforated at 5 depths below ground level: 180’, 360’, 830’, 1,125’ and 1,620’. <br />Five cement stages were pumped, to P&A the well, from 1,708’ to surface. The <br />casing was cut off below ground level and a plaque installed to identify the well <br />per regulation. <br />• NS conducted discrete zone water sampling of the DS-3, DS-6, DS-7, and DS- <br />10 wells for annual water quality analysis on June 25, 2024. <br />• Between September 9th and 12th Red Rock Well Service worked on the 12H- <br />IR well to clear a sediment obstruction in the wellbore. 12H-IR well returned to <br />service on the 13th. <br />• The NS 18H-IR-W redrill production well drilling operations started on October <br />8th, 2024. Drilling operations were completed on October 28th and the Capstar <br />Drilling Rig #330 rig was released to be demobilized off the NS lease. Hydraulic <br />connection of the 18H-IR-W and 18H-1V production wells was not immediately <br />established at the end of drilling operations. Completion operations to connect <br />the 18H-1V and 18H-IR-W production wells continued in November and <br />December with the Red Rock Well Service workover rig but were unsuccessful. <br />Additional connection operations will be undertaken during the second quarter <br />of 2025. <br />• NS pulled the recovery pump from the 12H-IR production well and installed it <br />in the 12H-R production well. Going forward, the 12H-IR will be the injection <br />well and the 12H-R will be the recovery well, the mining direction will be from <br />West to East.