Cripple Creek&Victor Gold Mine <br /> Valley Leach Facility Expansions <br /> Detailed Design for Permitting 1111 <br /> NewFields Project No.475.0106.064. <br /> March 2024 <br /> The subgrade will be scarified, moisture conditioned and re-compacted prior to the <br /> placement of structural fill. <br /> The Structural Fill will be placed and compacted in accordance with the Technical Specifications. <br /> 4.4.2. Lined PSSA Basin <br /> The VLF1 Phase 6 lined PSSA Basin is located upstream of the VLF1 Phase 6 PSSA Embankment <br /> and is sized to hold 132.8 million gallons, which exceeds the minimum storage required as <br /> determined from the water balance of 27 million gallons discussed below in Section 6.0. <br /> The liner system for this PSSA will consist of the following: 12 inches of SLF, with a 1x10-6 <br /> centimeters per second (cm/s)or lower permeability,overlain by a 100-mil double sided textured <br /> LLDPE geomembrane, overlain by three (3) feet of low volume solution collection fill (LVSCF), <br /> overlain by a 100-mil double sided textured LLDPE geomembrane with a permeability of about <br /> 3.25 x 10-9 m/s (Lee, Shin, & Kim, 2018), overlain by two to five (2-5)feet of DCF. Within the three <br /> feet of LVSCF will be a system of 4-inch diameter perforated corrugated polyethylene (CPe) pipes <br /> to assist in directing flow of the low volume solution to the collection system manifold, as <br /> described in Section 4.8.2 below. <br /> • <br /> 4.4.3. High-Volume Solution Collection Recovery System <br /> The High-Volume Solution Collection Recovery System (HVSCS) will direct process solution flows <br /> in the VLF1 Phase 6 PSSA area and into the Solution Recovery System (SRS). The High-Volume <br /> Solution Collection Recovery System, Solution Recovery System (HVSCS SRS) consists of four (4) <br /> 24-inch diameter carbon steel vertical riser pipes connected by a manifold fabricated using a 36- <br /> inch diameter SDR21 HDPE pipe for more efficient recovery.The pipes will house vertical turbine <br /> pumps to extract solution for further processing. The bottom 22 feet of the pipes will be slotted <br /> and fitted with a louvered screen to allow solution to enter the manifold. The vertical riser pipes <br /> will be extended vertically with the ore placement in the VLF1 Phase 6 PSSA. In order to reduce <br /> friction during fill placement and during any settlement that may occur, the pipes shall be <br /> wrapped in 100-mil smooth LLDPE geomembrane. Additionally, the pipes have been fitted with <br /> compression joints which will dissipate any force transmitted to the pipes via friction drag during <br /> settlement. This compression joint design has been previously used on other PSSA riser systems <br /> at CC&V. <br /> 4.5. Lined Pad Expansion Area <br /> The lined pad expansion will begin with lining upstream of the VLF1 Phase 6 PSSA and continue <br /> into the PSSA.Within the VLF1 Phase 6 PSSA,a leak detection system and composite liner systems <br /> will be installed below. The lining systems are described below. <br /> 1110 <br /> Page 13 <br />