CLIENT  <br />Newmont   <br />Cripple Creek & Victor Gold Mine  <br />PROJECT NO  <br />475.0106.049  <br />PROJECT: VLF2 Phase 3  <br />TITLE: TECHNICAL SPECIFICATIONS – Earthworks Construction  <br />Quality Assurance (CQA) Plan  <br />SPECIFICATION NO.  <br />01400 EARTHWORK CQA  <br />REV DATE PAGES  <br />APPROVALS  <br />REMARKS AUTHOR REVIEW CLIENT  <br />0 12/5/2019 10 JNM KCW Issued for Permitting  <br />1 12/17/2020 10 JNM KCW Re‐Issued for Permitting  <br />2 8/27/2021 10 JNM KCW Issued for Construction  <br />TABLE OF CONTENTS  <br />1.PART 1: INTRODUCTION ......................................................................................................... 1  <br />2.PART 2: DESCRIPTION OF PARTIES TO CONSTRUCTION QUALITY ASSURANCE ...................... 1  <br />2.1. CC&V ............................................................................................................................... 1  <br />2.2. Manager ......................................................................................................................... 1  <br />2.3. Design Engineer .............................................................................................................. 2  <br />2.4. Certifying Engineer ......................................................................................................... 2  <br />2.5. Construction Quality Assurance Monitor ........................................................................ 2  <br />2.6. Earthworks Contractor ................................................................................................... 3  <br />3.PART 3: LINES OF COMMUNICATION ..................................................................................... 3  <br />4.PART 4: DEFICIENCIES ............................................................................................................ 4  <br />5.PART 5: MEETINGS ................................................................................................................. 4  <br />5.1. Preconstruction Meeting ................................................................................................ 4  <br />5.2. Progress Meetings .......................................................................................................... 5  <br />5.3. Deficiency Meetings ....................................................................................................... 5  <br />6.PART 6: EARTHWORKS CONSTRUCTION QUALITY ASSURANCE ............................................. 5  <br />6.1. Construction Testing ....................................................................................................... 5  <br />6.2. Construction Monitoring ................................................................................................ 6  <br />6.2.1. Foundation Preparation ...................................................................................... 6  <br />6.2.2. Placement Of Materials ...................................................................................... 6  <br />7.PART 7: DOCUMENTATION .................................................................................................... 7  <br />7.1. Daily Record Keeping ...................................................................................................... 7  <br />7.2. Soils Observation and Testing Forms .............................................................................. 8  <br />7.3. Photo Documentation .................................................................................................... 8  <br />7.4. Design and Specification Changes .................................................................................. 8  <br />7.5. Weekly Progress Reports ................................................................................................ 8  <br />7.6. Construction Certification Report ................................................................................... 9