Laserfiche WebLink
4. Reclamation Timetable and Sequence <br /> The sequence and timing of reclamation can be seen in Table E-4 below. The reclamation <br /> schedule is dependent on the rate of mining and fluctuating market demands. The operator will <br /> reclaim the site concurrently with the progression of mining to limit the total disturbance. <br /> Table E-4 Reclamation Timetable <br /> Description Time Required <br /> Develop,mine,then reclaim Area 1 20 years <br /> Develop,mine,then reclaim Area 2.Area 1 2.5 years <br /> reclamation finalization and vegetation monitoring. <br /> Develop,mine,then reclaim Area 3.Area 2 20 years <br /> reclamation finalization and vegetation monitoring. <br /> Develop,mine,then reclaim Area 4.Area 3 5 years <br /> reclamation finalization and vegetation monitoring. <br /> Develop,mine,then reclaim Area 5.Area 4 2.5 years <br /> reclamation finalization and vegetation monitoring. <br /> Develop,mine,then reclaim Area 6.Area 5 3 years <br /> reclamation finalization and vegetation monitoring. <br /> Backfill,topsoil,and revegetate remaining 1 year <br /> disturbances <br /> Vegetation monitoring 2 years <br /> Total 56 years <br /> Limon Sand& Gravel Pit E-3 Lewicki&Associates <br /> August 2024 <br />