Mr.Joel Renfro <br /> RE: Tincnath Connell Pit M-1999-050 <br /> August 12,2024 <br /> The reclamation phasing and schedule is therefore: <br /> Reclamation Phasing and Schedule Summary <br /> Total Acreage Estimated <br /> Mine Phase (acres) Reclamation Completion <br /> Status (years) <br /> Phase 1 75 In Progress 8 - 10 <br /> Phase 2 45 Nearly Complete 1 -2 <br /> Phase 3 20 In Progress 4-6 <br /> 2. Yes, although the earth moving equipment will likely include dozers, loaders, scrapers, and <br /> excavators, any additional equipment necessary for mining and reclamation operations will <br /> also be used. Other equipment may include,but may not be limited to,water trucks,haul trucks, <br /> motor graders, compactors, and various sizes of dozers. <br /> 6.4.11 Exhibit K- Climate <br /> 3. Average monthly wind speeds (based on daily cumulative wind speed) were calculated from <br /> National Weather Service data collected at the Northern Colorado Regional Airport (NCRA) <br /> for the period July 2020 - August 2024. The NCRA is approximately 4.5 miles south of the <br /> project site. Additionally, average monthly wind speeds were obtained from the Western <br /> Regional Climate Center(period 1961 - 1990) for Denver, Colorado and Cheyene, Wyoming. <br /> AVERAGE MONTHLY WIND SPEEDS (MPH) <br /> Denver, Colorado Cheyene, Wyoming NCRA <br /> January 8.6 15.3 j 13.2 <br /> February 8.7 14.6 15.5 <br /> March 9.6 14.5 17.3 <br /> April 10.0 14.2 20.5 <br /> May 9.3 12.6 16.9 <br /> June 8.8 11.4 15.4 <br /> July 8.3 10.4 15.2 <br /> August 8.0 10.4 14.9 <br /> September 7.9 11.2 13.4 <br /> October 7.8 12.3 14.1 <br /> November 8.2 13.6 13.9 <br /> December 8.4 14.6 15.9 <br /> blue earth Page2of4 <br /> SOLUTIONS <br />