EXHIBIT C - Mining Plan <br /> Rule 6.3.3 <br /> The purpose of the mining plan is to describe how mining will affect the permit area for the duration of <br /> the operation. <br /> 1) Estimated dates of commencement: 4/1/2022 and completion: 5/31/2024 <br /> Note: Reclamation of all affected lands shall be completed within 12 months after issuance of the <br /> permit. An Operator possessing a 111(1)(b) Reclamation Permit must convert to the appropriate <br /> regular construction materials permit if extraction and export of materials from the site are not <br /> completed within 12 months after the issuance of the permit. <br /> 2) Depth of topsoil to be salvaged (check one): <br /> n 4-6 inches n 6-8 inches <br /> n 8-10 inches ❑ 10-12 inches <br /> n Other: <br /> n N/A, explain: <br /> 3) Description of how topsoil will be stockpiled and stabilized: <br /> Topsoil will be stockpiled as shown on the Exhibit E - Mining Plan map. and roughened to <br /> prevent erosion. <br /> 4) Thickness of overburden needed to be moved: feet or N/A N/A <br /> 5) Thickness of deposit to be mined: Ranges from 5 to 20 feet feet <br /> 6) How will the mine be accessed: (n) existing roads (n) new roads will be created <br /> a. Please describe the existing roads: <br /> The area will be accessed by an existing access to the north and a new access road to <br /> the south off of SH 13. See the mining plan maps. <br /> b. If there will be new roads or road improvements, please describe the new roads and road <br /> improvements (note, new roads must be included in permitted acreage): <br /> Road access will enter/exit at the existing road access and enter/exit at a new access to <br /> the borrow area site (new access meets up with existing access). <br /> 7) Will water be needed during the mining operation (check one): (❑)Yes or(E))No <br /> a. If yes,please describe the source of the water and how much water will be used during the <br /> operation: <br />