Laserfiche WebLink
Ninth Technical Revision (TR09) to Permit M-1973-021, Holcim- WCR, Inc. Morrison Quarry <br /> <br /> <br /> <br />January 2024 | 12 <br />and compaction. Overall slopes will range from 10H:1V to 2H:1V slopes, depending on target <br />location and reclamation requirements discussed in AM07. <br />For purposes of estimating these costs, it is assumed one (1) drilling and blasting operation, using a <br />Atlas Copco D65-T4F or equivalent, will be conducted to generate and load the material for transport <br />to the Satellite South Pit. Based on current drill and blast production rates at the quarry, it is <br />assumed that blasting will occur one to two-days per week and will generate approximately 40,000 <br />tons (29,412 LCY). The rest of the week will be used to load and transport material (discussed in <br />Item 2.2 below). Based on the 29,412 LCY per week production rate and 1,854.183 LCY needed for <br />backfill, drilling and blasting will take up to 16 months to complete. <br />Item 2.2 Mined Area Earthwork: Fill and Compaction <br />The average haul distance to the Satellite South Pit from the drilling and blasting location is up to <br />0.25 miles. Material will be loaded from the blast area using one (1) front-end wheel loader <br />(Caterpillar 992 or equivalent) and transported to the Satellite South Pit using three (3) rigid 100-ton <br />haul trucks (Caterpillar 777 or equivalent). All fill material will be placed and compacted using one (1) <br />CAT D9 bulldozer as follows: <br />· Placed in loose, horizontal lifts not to exceed 30-inches thick, assuming maximum rock sizes are <br />limited to two-thirds of the lift thickness <br />· Compacted to achieve greater than 80% of the maximum dry density determined in accordance <br />with ASTM D698 <br />· Placed in a manner that allows for a moisture content within 3% of optimum based on <br />ASTM D698 <br />Based on an estimated backfill requirement of 1,854,182 LCY, 6 days per week of operation and 12 <br />hour work days, it is assumed that it will take up to 16 months to complete fill and compaction <br />activities. <br />Item 2.3 Compaction Testing <br />Throughout backfill and compaction activities, quality assurance and quality control testing shall be <br />performed. Testing for in-place density and moisture content will be performed in accordance with <br />ASTM D6938, using nuclear testing methodology, and it is assumed this testing will be done once <br />per lift and each lift will take approximately 1 day to complete. Costs for QA/QC testing assume a <br />unit rate for each lift for reclamation of the Satellite South Pit. For purposes of cost estimating, it is <br />assumed up to 48 days (based on 48 anticipated lifts) will be needed to complete compaction <br />testing. <br />Item 3.0 Dewatering <br />During backfill operations, groundwater and surface water will be collected in sumps constructed <br />within the pit where water will collect and be pumped using an electric dewatering pump to Outfall <br />006 for discharge. As discussed in Section 2.3, a dewatering rate of 5 gallons per minute is <br />anticipated in the Satellite South Pit. Dewatering will also be needed to address any precipitation of <br />stormwater inflow (similar to current dewatering completed in the South Quarry as part of the mining <br />operations). For purposes of cost estimated, it is assumed that two (2) dewatering pumps (6”