Laserfiche WebLink
The State, acting by and through the Principal Representative, shall have the authority to suspend <br /> the work, either wholly or in part, for such period or periods as he or they may deem necessary due <br /> to: <br /> (a) Unsuitable weather; <br /> (b) Faulty workmanship; <br /> (c) Improper superintendence <br /> (d) CONTRACTOR failure to carry out orders or to perform any provision of the Contract <br /> Documents; <br /> (e) Conditions which may be considered unfavorable for the prosecution of the work. <br /> Additional time will be added to the performance time for the contract for (a) above only. <br /> If it should become necessary to stop work for an indefinite period, the CONTRACTOR shall store <br /> all materials in such manner that they will not become an obstruction or become damaged in any <br /> way; and he shall take every precaution to prevent damage to or deterioration of the work, provide <br /> suitable drainage and erect temporary structures where necessary. <br /> Such Suspend Work Order shall be in writing and the CONTRACTOR shall again proceed with the <br /> work when so notified in writing. <br /> Article 35. ESTIMATED QUANTITIES <br /> The CONTRACTOR understands and agrees that: <br /> (a) The quantities and measurements set forth in the Special Conditions are in no case <br /> exact and in some instances the exact quantities and measurements are impossible <br /> to determine until after conditions have become known during construction; <br /> (b) The quantities shown in the Special Conditions are for use as a basis for comparing <br /> bids only; <br /> (c) The Principal Representative does not expressly, or by implication, agree that the <br /> actual amount of work performed or material furnished or installed will correspond <br /> therewith; <br /> (d) During the progress of the work the Principal Representative may find it advisable and <br /> shall have the right to make changes in locations of portions of the work, to omit <br /> portions of the work and to increase or decrease the quantities, as may be deemed <br /> necessary or desirable; <br /> (e) Under no circumstances or conditions will the CONTRACTOR be paid anything on <br /> account of anticipated profits upon the work or any portion thereof covered by the <br /> Contract which is not actually performed; <br /> (f) Under no circumstances or conditions will the CONTRACTOR be paid more than the <br /> unit price bid for any item of the Bid because the actual quantity is greater or less than <br /> the quantity shown in the Bid or Bid Schedule, and <br /> Colorado Division of Reclamation, Mining and Safety <br /> Page 13 of 22 Pages <br /> Revised:9/17/2019 <br />