be made as this item is completed and approved by the PROJECT MANAGER. Payment <br /> for this item will be made only on the final (before retainage) invoice. <br /> TASK 3.0 REDUCE HIGHWALLS AROUND PIT PERIMETER <br /> The reclamation of the Hanna site includes reducing the highwalls around the perimeter <br /> of the pit. Some highwalls are six to eight (6-8) feet above the groundwater elevation. <br /> Approximately one thousand linear feet (1,000 LF.) of highwalls will be graded to a <br /> 3H:1 V slope. See attached map for further details. <br /> Highwall elimination shall start approximately fifteen feet (15 ft.) back from the edge of <br /> the pit walls. Material shall be cut and removed to achieve an overall slope of 3H:1 V. The <br /> material cut to eliminate the highwall shall be placed directly into the pit. <br /> A large depression is present at the northeast corner of the pit. Two hundred twenty five <br /> cubic yards (225 CY) of stockpiled topsoil will placed in the depression to reduce the <br /> vertical side slopes of the pit. <br /> The Division estimates approximately three thousand cubic yards (3,000 yd3) of <br /> material is required to be cut to eliminate the highwall to a 31-1:1 V slope or less, as directed <br /> by the PROJECT MANAGER. If adequate material is not available from excavation to <br /> reduce the gradient of the side slopes, topsoil from the existing adjacent stockpile will be <br /> placed on the pit slope until a 31-1: 1V slope is achieved. Seventy five cubic yards (75 <br /> CY) of topsoil from the stockpile is required to reduce the highwalls. This task <br /> includes transport and placement of the topsoil from the stockpile to the pit. <br /> Please note these figures are estimates of the material that will need to be graded into <br /> the pit. CONTRACTORS are responsible for verifying all estimates prior to bid submittal. <br /> Measurement and Payment <br /> There will be no measurement for payment. Payment for this task will be reflected in a <br /> lump sum quote under Item 3.0 on the Bid Schedule. This lump sum quote will cover all <br /> costs for this task including equipment, maintenance, supplies and operator costs. <br /> Payment shall be made as this task is completed and approved by the PROJECT <br /> MANAGER. <br /> TASK 4.0 GRADE PIT FLOOR AND APPLY TOPSOIL <br /> The eastern portion of the pit floor contains piles of cobble and rock and is devoid of <br /> vegetation. Approximately 0.33 acres of pit floor will be graded and four to five inches (4 <br /> in. to 5 in.) of topsoil will be distributed evenly over the barren area. Compacted areas will <br /> be ripped prior to seeding. See attached map for further details. Two hundred cubic <br /> yards (200 CY) of stockpiled topsoil is required for this task. <br /> This task includes transport and placement of the topsoil from the stockpile to the pit. <br /> Page 9of11 <br />