Laserfiche WebLink
Ninth Technical Revision(TR09)to Permit M-1973-021,Holcim-WCR,Inc.Morrison Quarry FN <br /> 3.3 Planned Satellite South Pit Reclamation Scope of Work <br /> Item 1.0 Mobilization/Demobilization <br /> This item includes all costs necessary and incidental to move equipment and supplies onto the <br /> project area; move equipment within the project area during the course of the project; and fulfill any <br /> other requirements necessary for the successful completion of this project. The operator will <br /> maintain such temporary works and equipment throughout the period of construction. This item also <br /> includes all labor, equipment, and costs associated with demobilization and clean-up of the project <br /> site following completion of the project. For the scope of work proposed, Holcim assumes that the <br /> following equipment will be mobilized to the site (this equipment list is the equipment currently used <br /> by Holcim for production and reclamation activities at the Quarry): <br /> • (2) Surface Drills (Atlas Copco D65-T4F or equivalent) <br /> • (2) Skid-Steer Loaders (Caterpillar 226D or equivalent) <br /> • (4) Front-end wheel loaders with a 15-cubic-yard bucket (Caterpillar 992 or equivalent) <br /> • (2) Bulldozers (Caterpillar D9 or equivalent) <br /> • (8) Rigid 100-ton haul trucks (Caterpillar 777 or equivalent) <br /> • (2) Water Trucks (Caterpillar 725C2 Modified - 10,000 gallons, or equivalent) <br /> This equipment will most likely be provided by the operator. The loading, hauling, and grading <br /> equipment can also be rented from Wagner Rents—Caterpillar Rental, 17800 E. 22nd Avenue, <br /> Aurora, Colorado 80011. The drill and blasting equipment and services can be procured from <br /> qualified contractors in the area. Costs for reclamation assumed loading, hauling, and grading <br /> equipment rental and procurement of a qualified drilling and blasting contractor. <br /> Item 2.1 Mined Area Earthwork: Drilling and Blasting <br /> As described in Section 3.2, it is anticipated that fill material will need to be generated on-site to <br /> provide sufficient material to complete the Satellite South Pit backfill activities. This material will <br /> be generated in the South Quarry in the footprint approved under AM07 and is anticipated to be <br /> completed concurrent with Satellite South Pit reclamation activities. Drilling and blasting will be <br /> completed using drill and blast methods currently employed at the site (refer to AM05 for drill <br /> and blasting methods). Overall slopes will range from 1 OH:1V to 2H:1V slopes, depending on <br /> target location and reclamation requirements discussed in AM07. The location(s) for generation <br /> of additional fill material will be focused on areas that will assist with final site grading and <br /> reclamation. Once drilling and blasting is complete, material will be transported to the Central <br /> Quarry where it will be segregated and stockpiled for use as fill material. <br /> For purposes of estimating these costs, it is assumed that two concurrent drilling and blasting <br /> operations will be conducted to generate and load the material for stockpiling. To complete <br /> drilling and blasting via two concurrent operations, two surface drills (Atlas Copco D65-T4F or <br /> equivalent), two skid-steer loaders (Caterpillar 226D or equivalent), and two front-end wheel <br /> loaders (Caterpillar 992 or equivalent) will be used. Four rigid 100-ton haul trucks (Caterpillar <br /> 777 or equivalent) will be used to haul material from the two drill/blast locations to the Central <br /> October 2023 1 11 <br />