Construction Schedule <br /> • Expected start date 10/2/2023 (subject to change based on TR approval). <br /> • Some tasks overlap. <br /> • Note that electrical work will be self-performed by Climax and due to supply chain issues, <br /> certain long-lead components may not be available until after the civil construction work is <br /> complete. Leak testing and other activities that require electricity will be powered with a <br /> mobile generator. <br /> Task Estimated Start date Estimated Task Length <br /> Survey 10/2/2023 5 days <br /> Mobilization 10/7/2023 1 day <br /> Dewatering, set-up, and 10/8/2023 9 days <br /> maintenance <br /> Demolition of inlet headwall on 10/12/2023 1 day <br /> 120-inch dia. culvert <br /> Install cutoff structure 10/13/2023 9 days <br /> Install wet well 10/23/2023 2.5 days <br /> Install grating and beam, discharge 10/26/2023 4.5 days <br /> pipe, 18-inch diameter pipe, <br /> submersible pumps and valves in <br /> pump house <br /> Perform leak test on pump station 11/1/2023 0.5 days <br /> discharge pipes <br /> Install pump house concrete slab 11/2/2023 2.5 days <br /> Install pump house 11/7/2023 8 days <br /> Install 8-inch diameter HDPE 11/9/2023 12.5 days <br /> discharge pipe <br /> Perform leak test on 8-inch HDPE 11/22/2023 0.5 days <br /> pipe <br /> Plug culverts 11/27/2023 1 day <br /> Punch list items 11/28/2023 2 days <br /> Electrical (by Climax) TBD based on availability of 2 weeks <br /> electrical components <br /> Clean-up and demobilization of 12/1/2023 1 day <br /> civil contractor <br />