Cost Summary Worksheet Cont'd Task#000 Page 2 of 4
<br /> 065 Rip West Ash Haulroads(West Ash,West Ashl RIPPER 4 5.98 $9,474
<br /> and West Ash 2)
<br /> 066 Rip LOM Haul Roads(F2 and F2-G5) RIPPER 4 8.76 $13,879
<br /> 067 Rip A Pit Haul Roads(Middle A and North A) RIPPER 4 6.43 $10,184
<br /> 068 Rip N Pit Haul Roads RIPPER 4 5.38 $8,526
<br /> 072 Rip East A Haul Roads(East A and East A Split) RIPPER 4 2.96 $4,690
<br /> 074 Rip Access Road(Tasks 042-059) RIPPER 4 3.11 $4,926
<br /> 075 Rip K Pit Haul Roads(KMain,Kl,K2 ,K3) RIPPER 4 2.12 $3,363
<br /> 077 Rip I/J Roads(UJ Spoil,I Mid,I West) RIPPER 4 4.55 $7,214
<br /> 078 Regrade Coyote Impoundment DOZER 2 288.69 $208,963
<br /> 079 Regrade Middle Pyeatt Impoundments DOZER 1 51.73 $18,721
<br /> Impoundment(1,2,3)
<br /> 080 Regrade Far East Buzzard Impoundment DOZER 1 0.56 $204
<br /> 081 Regrade Sage Impoundments(1 and 2) DOZER 1 18.91 $6,845
<br /> 082 Regrade West Horse Impoundment DOZER 1 3.52 $1,273
<br /> 083 Regrade Impoundment H DOZER 1 7.29 $2,637
<br /> 084 Regrade Industrial Waste Pond DOZER 1 7.47 $2,703
<br /> 085 Regrade Deal 1 and 2 DOZER 1 9.83 $3,835
<br /> 086 Regrade Deacon 1,2 and Jeffway 1,2 DOZER 1 94.72 $36,962
<br /> impoundments
<br /> 087 Regrade W.Buzzard#4 Impoundment DOZER 1 6.00 $2,343
<br /> 088 Regrade E.Buzzard#3 Impoundment DOZER 1 7.04 $2,747
<br /> 089 Regrade Diversions DOZER 1 61.42 $17,231
<br /> 090 Re lace Topsoil on Ash Pits(ASH1) SCRAPERI 1 5.20 $29,208
<br /> 090A Replace Topsoil on Ash Pits(ASH2) SCRAPERI 1 12.78 $71,735
<br /> 090B Replace Topsoil on Ash Pits(A92-4 to Pit) TRUCKI 1 107.16 $259,367
<br /> 091 Replace Topsoil on D/E Pits(Truck/Excavator) TRUCKI 1 416.57 $873,326
<br /> 091A Replace Topsoil on D/E Pits(D97-1) SCRAPERI 1 14.75 $79,262
<br /> 091B Replace Topsoil on D/E Pits(D1-07) SCRAPERI 1 1.99 $10,706
<br /> 092 Replace Topsoil at C Pit SCRAPERI 1 91.03 $511,131
<br /> 096 Replace Topsoil at West Panel,BC rd,Shop SCRAPERI 1 13.22 $74,249
<br /> (Scraper)
<br /> 096A Replace Topsoil at West Panel,BC rd,Shop TRUCKI 1 147.14 $308,466
<br /> (Truck/Excavator)
<br /> 097 Replace Topsoil at East Panel Ponds,A road SCRAPERI 1 20.64 $115,897
<br /> (Scraper)
<br /> 097A Replace Topsoil at East Panel Ponds,A Rd TRUCKI 1 209.29 $438,768
<br /> (Truck/Excavator)
<br /> 098 Re-topsoil Johnson Coal Stockpile SCRAPERI 1 4.14 $23,254
<br /> 099 Replace Topsoil at Dragline Walk Road(ASH4) TRUCKI 1 8.17 $14,484
<br /> 099A Replace Topsoil at Dragline Walk Road(ASH I) TRUCKI 1 33.14 $58,752
<br /> 100 Facilities Area REVEGE 1 75.00 $28,037
<br /> 100A Seed D Pit Range A-B REVEGE 1 319.30 $220,117
<br /> 101 Roads(including BC road)below 6700' REVEGE 1 196.00 $73,382
<br /> 102 Finish Grading UJ Pit GRADER 2 21.73 $13,139
<br /> 103 Ponds below 6700'(Coyote,Sage,E Buzzard) REVEGE 1 26.00 $9,719
<br /> 104 Johnson Coal Stockpile REVEGE 1 12.00 $4,710
<br /> 105 topsoil piles below 6700' REVEGE 1 27.00 $10,131
<br /> 107 Roads:>6700 ft.-Rangeland with Shrubs REVEGE 1 54.00 $37,364
<br /> 108 Ash pit.-Rangeland with Shrubs REVEGE 1 115.00 $79,691
<br /> 109 Seed D/E Pit Range B REVEGE 1 15.00 $10,331
<br /> 111 Ponds above 6700'(Deal,Deacon,Jeffways,West REVEGE 1 19.00 $12,898
<br /> Horse)
<br /> 112 topsoil piles above 6700' REVEGE 1 5.00 $3,516
<br /> 113 Shrub Transplants as per operator NA 1 40.00 $155,204