Laserfiche WebLink
Colorado Inactive Mine Reclamation Program <br /> CLOSEOUT REPORT <br /> ACTIVE MINE BOND FORFEITURE PROJECTS <br /> Permit Information <br /> Permit Number: Operator Name: Mine Name: <br /> P-2007-047 CHM Ventures, LLC Summit Point Exploration <br /> Type of Mine— NOI Commodity Mined— Uranium <br /> PRE-RECLAMATION SITE CONDITIONS <br /> The Summit Point Exploration site is located 9.5 miles north of Egnar, on the west side of Summit Canyon in San Miguel <br /> County, Colorado on land administered by BLM. This was an NOI operation permitted for 3 acres of disturbance to assess <br /> the mineral potential via up to 6 drill hole exploration to depths of up to 2,500 feet. The required Financial Warranty held is <br /> $21,204.00. In May 2016, the Mined Land Reclamation Board revoked the NOI permit and ordered that the Financial <br /> Warranty be forfeited. The site requires further reclamation, including drill hole abandonment, re-grading sump pits, erosion <br /> control, weed control, and revegetation on three drill hole pads totaling about 1.5 acres. The funds available to accomplish <br /> this were from the Summit Point Exploration Bond. <br /> BIDDING/CONSTRUCTION INFORMATION <br /> Type of Bid— Discretionary Purchase <br /> PO Number: Contractor Name &Address: Construction Bond Amount(after 5% administrative <br /> PO-PKAA- Red Dog Enterprises Dates: fee removed)-$20,143.80 <br /> 201800004421 PO Box 452 <br /> PO Date: 9/12/17 Hotchkiss, CO 81419 Start: 10/2/17 Project Cost-$20,134.80 <br /> End: 10/6/17 <br /> Construction Work Description <br /> Construction began on October 2, 2017 with equipment and materials being mobilized to the project site. The Contractor <br /> first sprayed noxious weeds before beginning earthwork. The casings were capped with schedule 40 steel caps bolted with <br /> three 3/8 inch threaded bolts drilled into the casing and cut flush with the outside of the cap to provide a permanent cover for <br /> the drill holes. The earthen sumps were re-graded to match the surrounding topography and a series of berms were <br /> constructed to control water runoff along an existing access road near drill pad 6. Finally, the drill pads and disturbed areas <br /> were revegetated by spreading seed and spreading weed-free mulch and fertilizer to promote beneficial species growth. <br /> A total of approximately 1.5 acres were reclaimed. <br /> The total cost for this work was $20,134.80. The project was completed on 10/6/17. <br /> Remaining Reclamation Requirements and Estimated Cost: <br /> The reclamation for the NOI permit was completed with the bond monies; however, ongoing weed control may be required <br /> until vegetation can re-establish in the area. <br /> Prect Manager Senior Project Manager <br /> tpira- <br /> (D1tiqf <br /> Date Date <br />