Colorado Inactive Mine Reclamation Program <br /> CLOSEOUT REPORT <br /> MAINTENANCE PROJECTS <br /> OSM Number—466 <br /> Severance Tax — FMS8 <br /> Maintenance Project Name —Alaska Basin Maintenance and Forfeiture Project <br /> rORIGINAL MINESITE INFORMATION <br /> Project Number: Feature Numbers: 38, 39, 40, 41a, Feature Types — stopes, shafts, <br /> PKA-10-1160 & 41 b, and mine waste piles <br /> REASON MAINTENANCE NEEDED—After two previous projects, the Maid of the Mist 2004 <br /> Project and the Alaska Basin 2006 Project, maintenance and completion of mine closures was <br /> needed. Both of the previous projects encountered problems due to early snow and early winter <br /> shut-downs. In 2006, the Alaska Basin contractor attempted to close mine opening 38, but <br /> found the site to be significantly larger after the adit collapsed and opened into a stope. Mine <br /> openings 41a and 41b also needed additional backfill because of settling, most likely from the <br /> two on-site school buses buried in the stopes. The 2009 project also addressed post 1977 <br /> mining activity at the number 40 shaft, and the number 39 waste piles located in an active <br /> stream channel. <br /> BIDDING/CONSTRUCTION INFORMATION <br /> Type of Bid: Documented Quote <br /> Bid as part of the Alaska Basin Maintenance and Forfeiture Project, PKA-10-1160 <br /> PO Number: Contractor Name & Address Construction Dates Cost <br /> OE PKA-10-14 K and P Property Designs Start $11,680.00 <br /> 236 South 3rd#219 8/20/09 <br /> PO Date: Montrose, CO 81401 <br /> End <br /> 8/13/09 9/21/09 <br /> Construction Work Description —Alaska Basin Maintenance and Forfeiture construction started in <br /> late August 2009 and proceeded into mid-September 2009. Site 40 was changed from a grate to <br /> backfill during construction because the site's conditions were more suitable to backfill due to <br /> unconsolidated bedrock and mine waste at the site's surface. Site 40 should be monitored for <br /> settling of the backfill. Snow remained on site 38 well into late August and 38 had to be shoveled <br /> As of 05/14/09 <br />