MR-9 updated the steepness of the side slopes for overburden and topsoil stockpiles. MR-9 was <br /> issued on September 4, 2013. <br /> MR-10 proposed to install groundwater monitoring wells GW-N56, GW-N57, and GW-N58, <br /> modify mine facilities and haul road construction. MR-10 was withdrawn on October 29, 2013. <br /> MR-11 changed irrigation designs, and incorporated Air Permit No. 10M02275F. MR-I I was <br /> issued on January 24, 2014. <br /> MR-12 updated identification of interests. MR-12 was issued on February 20, 2015. <br /> MR-13 updated the reclamation cost estimate. MR-13 was issued on May 21, 2015. <br /> MR-14 updated seed mix 93. MR-14 was issued on June 5, 2015. <br /> MR-15 changed the mining timing within the already approved mining area. MR-15 was issued <br /> on September 3, 2015. <br /> MR-16 removed the coal stockpile limit of 10,000 tons. MR-16 was issued on February 24, <br /> 2016. <br /> MR-17 proposed to update the identification of interests. MR-17 was withdrawn on July 20, <br /> 2016. <br /> MR-18 added a spring seeding window of April 1 to May 31 for the dryland pasture. MR-18 <br /> was issued on April 7, 2017. <br /> MR-19 incorporated two permit stipulations into the permit application text. MR-19 was issued <br /> on May 18, 2017. <br /> MR-20 extended the 180-day requirement for completion of backfill and grading, and updated <br /> the reclamation timetable and air pollution control permit. MR-20 was issued on July 10, 2017. <br /> MR-21 updated the Air Pollution Control Permit, updated Section 2.05.3(4), and addressed the <br /> movement of Bench 1 material on the Garvey property to accommodate the installation of the <br /> CCC Ditch pipeline. MR-21 was issued on October 3, 2017. <br /> MR-22 provided updates to the Personal Injury and Property Damage Insurance documents. <br /> MR-22 was issued on October 3, 2017. <br /> MR-23 provided updates to Map 2.04.7-9 and Map 2.05.4(2)(e)-1 to show the final location of <br /> the CC Ditch Company 2nd Park Lateral pipeline. MR-23 was issued on March 21, 2018. <br /> MR-24 provided updates to Map 2.05.4(2)(d)-2 and the topsoil redistribution plan. MR-24 was <br /> issued on March 1, 2018. <br /> 7 <br />