Laserfiche WebLink
amec <br /> foster <br /> wheeler <br /> Zephyr Gold USA Ltd. PAGE 9 OF 13 <br /> Dawson Gold Project <br /> Dawson Filtered Tailings Storage Facility SPECIFICATION SEC. NO.: <br /> 01400.2 <br /> Pre-feasibility Study TECHNICAL SPECIFICATIONS FOR DATE: (ORIGINAL) <br /> Fremont County, Colorado GEOSYNTHETICS CONSTRUCTION QUALITY 20-October-16 <br /> PROJECT NO.: 74201633 ASSURANCE(CQA) PLAN REVISION: A <br /> DATE: 20-Oct-16 <br /> for lunch,weather conditions, etc.) of 30 minutes or more for each seaming apparatus used that day. Each <br /> Seamer shall make at least one trial seam each day. Seaming operations shall not commence until the <br /> CQA MONITOR(S)has determined that the seaming process is meeting the SPECIFICATION requirement <br /> and is acceptable. The CQA MONITOR(S)shall record the trial weld results on the trial seam log form. <br /> Field Seaming-The CQA MONITOR(S) shall verify that only approved equipment and personnel perform <br /> welding, all welding is performed under suitable conditions as specified in the project SPECIFICATIONS, <br /> specified overlaps are achieved, seams are oriented in compliance to project requirements, and that <br /> grinding techniques and extrudate meet project requirements for extrusion welding. The CQA <br /> MONITOR(S)shall record all field seaming on field seaming log forms. <br /> Non-Destructive Seam Continuity Testing- The CQA MONITOR(S) shall verify that the seams and repair <br /> are non-destructively tested by CQC personnel in compliance with the project SPECIFICATIONS. If a seam <br /> cannot be tested, the CQA MONITOR(S) shall ensure that CQC monitors observe cap strip operations. <br /> The CQA MONITOR(S) shall verify that test equipment and gauges are functioning properly and that test <br /> procedures are in compliance with the project SPECIFICATIONS. The CQA MONITOR(S)shall verify that <br /> the seams and repairs with failing test results are repaired and/or re-tested until passing results are <br /> achieved. The CQA MONITOR(S)shall record observed non-destructive test locations on the vacuum test <br /> and pressure test log forms. <br /> Destructive Seam Testing - The INSTALLER shall obtain samples, at locations selected by the CQA <br /> MONITOR(S), of the field seamed geomembrane approximately 24 in along and 12 in across the seam and <br /> centered over the seam as follows: <br /> • A minimum of one sample for each geomembrane Seamer. <br /> • A minimum of one sample every 500 feet of seaming is required unless, in the opinion of the CQA <br /> MONITOR(S) and ENGINEER, the Seamer has demonstrated sufficient quality/experience to <br /> increase the seam sample interval. In no event shall the sampling interval exceed 1000 feet. <br /> • Seams that appear suspect to the CQA MONITOR. <br /> • The CQA MONITOR(S) shall witness the testing of destructive seam samples by the <br /> INSTALLER'S CQC personnel. The INSTALLER shall mark all samples with their roll and seam <br /> number, date, machine number, welding technician identification, extruder and nozzle/wedge <br /> temperature, and ambient air temperature. <br /> • The INSTALLER shall test all destructive samples in compliance with the project <br /> SPECIFICATIONS. <br /> S:\ZEPHYR MINERALS\DRMS MINE APPLICATION\01400.2-GEOSYNTHETICS CQA.DOCX <br />