Exhibit D Mining Plan (cont) <br /> REVISION 2 - Revised Timetable <br /> The Mining Timetable has been updated to show the current <br /> conditions in Lake Robert and revisions to the other stages based <br /> on the existing permit conditions and proposed changes . It is an <br /> estimate based on an average year, and McAtee Construction Company <br /> expects some years to vary widely from the average. If there are <br /> changes in the mining timetable, we will discuss the reasons for <br /> the change in the annual report that follows the change and modify <br /> it at that time if needed. <br /> Mining Timetable <br /> ACRES <br /> STAGE YEARS MINED MINING SLOPE <br /> Lake Robert complete 7 . 95 3 . 05 4 . 90 <br /> Lake 6-10 27 . 15 11 . 30 15 . 85 <br /> Marjorie <br /> West Lake 3-5 18 . 16 7 . 31 10 . 85 <br /> East Lake 1 10-12 124 . 18 12 . 95 11 .23 <br /> TOTALS 1 177 . 44 1 34 . 61 1 42 . 83 <br /> MCATEE CONSTRUCTION COMPANY RIVERSIDE PIT <br /> PERMIT#M-1976-056 AMENDMENT 1/14/2022 <br /> 8 <br />