J & P TRUCKING CALICHE PIT <br /> Exhibit D <br /> Mining Plea <br /> The sequence of mining will be to begin excavation in Phase 1 <br /> area, then proceed through the phases, in the order they are <br /> numbered. Phase 1 will affect approx. 10 acres, and will <br /> utilize an approximately 1 acre haul road that will proceed <br /> northwest from the main pit entrance to the Phase 1 area. <br /> The main pit entrance is accessed via an existing two track <br /> road that is currently used by the landowners for farming <br /> purposes, and will be left in place for farm use following <br /> mining completion. Phase 1 will begin in the northwest end of <br /> a previously started pit (depicted on topographical maps in <br /> Exhibit C), located in the Northwest Quarter of the proposed <br /> permitted area. As depicted on the maps in Exhibit C, Phase 1 <br /> contains approx. 3 acres in the corner of an irrigated circle, as <br /> well as being part of the irrigated circle. Said 3 acres is a ridge <br /> of desired caliche material that is to be removed at the request <br /> of the landowner so that the center pivot sprinkler will operate <br /> as desired. A screener and possibly crusher will be placed in <br /> the northwest end of the area that was disturbed/affected by <br /> the previous gravel operation inside the boundaries of Phase <br /> 1, and will be moved as the mining progresses within the <br /> boundaries of Phase 1. Excavation will then proceed in a <br /> South/Southeasterly direction inside the boundaries of Phase <br /> 1 with the use of loaders and an excavator. No explosives are <br /> needed or will be used. The type of overburden is <br /> topsoil/black dirt, ranging approx. 1 to 4 inches thick, with the <br /> exact make-up of the stratum immediately beneath the <br /> material being unknown. The nature of the deposit is caliche, <br /> depth is shallow, thickness is approx. 4 to 20 feet. The topsoil <br /> will be stockpiled along/within the boundaries of the phase <br /> being mined and left in place until it is needed for re-topsoiling. <br /> Topsoil stockpiles will be re-seeded with western wheatgrass <br /> to prevent erosion if said stockpiles are to be left in place <br /> longer than one <br />