Laserfiche WebLink
The project will involve the development of the gravel pit, including two phases. <br /> Phase I—approximately 4 acres,vegetation and trees will be removed and processed, removal and <br /> stockpile of topsoil (save what we can get for reclamation), construction of berm for the 25ft buffer, and <br /> ditches. Access road will be cut in and berm at least 3 ft high for safety,18 inch culvert will be installed. <br /> create a processing area approximately 1.5 acres, cut pad and ditches,and berm along the north side of <br /> pit for pit containment and water diversion,4" rock containment pond.The railroad grade created a <br /> sediment pond and a dry dam for drainage.This plan reduces the severity of the storm water during <br /> construction operations. Berms and ditches will be monitored.The date of commencement is estimated <br /> to be 2020.This stormwater plan will be in place prior to crushing activities. Having two phases will limit <br /> the disturbed area of the site, and will help with reclamation. <br /> IV <br /> "t x <br />