Laserfiche WebLink
Mica Lode, Permit M-1977-144,Technical Revision <br /> Exhibit L-Reclamation Costs <br /> The figures below are taken from the individual task details described in Exhibit E. <br /> Reclamation Costs and Estimated Financial Warranty Amount <br /> Affected Area <br /> Reclamation Tasks: Quantities x Unit Costs Task Cost <br /> Ruby Pit <br /> Slope grading: D8 dozer or equivalent on 4.0 acres of slopes, 16 hours @ $100.00/hr. 1600. <br /> Pit floor grading(if pit is not a pond): D8 or equiv.on 1.0 ac.floor, 3 hrs @ $100.00/hr. 300. <br /> Seedbed prep: spread growth medium & rip, D8 or equiv., 6 hrs @ $100.00/hr. 600. <br /> Placement of oversize material in pit: Cat 830 loader or equiv., 150 CY @ $2.50/CY. 375. <br /> Seeding(all areas): 5.0 acres @ $1,000/ac. (+ 30%for reseeding) 6500. <br /> IMC-2 Quarry <br /> Slope reduction: blasting and grading with D8 or equiv.,4,000 CY @ $1.00/CY. 4000. <br /> Slope finish grading:4 hrs @ $100.00/hr. 400. <br /> Pit floor grading: 2 hrs @ $100.00/hr. 200. <br /> Seedbed prep: spread medium and rip, D8 or equiv.w/ripper, 3 hrs @ $100.00/hr. 300. <br /> Seeding(all areas): 2.5 acres @ $1,000/ac. (+ 30%for reseeding) 3250. <br /> IMC-3 Quarry <br /> Haul backfill material: Cat 830 loader, 12-yd dump truck, 6 hrs @ $150/hr. 900. <br /> Spread material: D8 or equiv., 2 hrs @ $100.00/hr. 200. <br /> Finish grading and seedbed prep: D8 or equiv.w/ripper,4 hrs @ $100.00/hr. 400. <br /> Seeding: 1.0 ac @ $1,000/ac. (+30%for reseeding) 1300. <br /> MQD-1 Dump (West Dump) <br /> Slope reduction: D8 or equiv., 3,500 CY @ $1.00/CY. 3500. <br /> Haul growth medium: Cat 830 loader, 12-CY dump truck, 1,000 CY @ $1.50/CY. 1500. <br /> Spread growth medium: D8 or equiv., 6 hrs @ $100.00/hr. 600. <br /> Finish grading: D8 or equiv., 8 hrs @$100.00/hr. 800. <br /> Seedbed prep: D8 w/ripper, 6 hrs @ $100.00/hr. 600. <br /> Seeding: 6.0 ac @ $1,000/ac. (+30%for reseeding) 7800. <br /> MQHW-1 (West Highwall) <br /> Slope reduction by drilling and blasting: 2,000 CY @ $2.00/CY. 4000. <br /> Pushing and rough grading shot rock: 1,000 CY @ $1.00/CY. 1000. <br /> Placing and spreading waste rock and fines on benches: 1,000 CY @ $1.00/CY 1000. <br /> Seeding benches and unmined margins: 2.1 ac @ $1,000/ac. (+30%for reseeding) 2730. <br /> MQEW-1 (East Highwall) <br /> Slope reduction by drilling and blasting: 1,700 CY @ $2.00/CY. 3400. <br /> Pushing and rough grading shot rock: 1,000 CY @ $1.00/CY. 1000. <br /> Placing and spreading waste rock and fines on benches: 1,000 CY @ $1.00/CY 1000. <br /> Seeding benches, slope, and margins: 1.6 ac @ $1,000/ac. (+30%for reseeding) 2080. <br />