RECLAMATION PLAN EXHIBIT E(CONT) <br /> RECLAMATION TIMETABLE <br /> Reclamation will begin once enough area has been opened so <br /> that any reclamation completed will not be disturbed as mining <br /> progresses . This may take 5 or more years depending on the <br /> economic conditions in the area and the amount of material mined. <br /> The operator anticipates approximately 80% of the total mined <br /> land will be reclaimed by the time mining is completed. A <br /> portion of the floor area will be complete, but the area under <br /> the stockpile area will still need work and grading of the final <br /> face area will be the last area to be reclaimed. <br /> Within one year after the stockpiles have been removed, all <br /> resoiling will be complete . The revegetation may take longer <br /> depending on how the farm manager chooses to use the site once it <br /> is graded and resoiled. The area will then be monitored for <br /> success of revegetation until the reclamation responsibilities <br /> are released. The operator estimates that, this will happen 1 to <br /> 3 years after mining is completed, since for crop land <br /> reclamation success is evidenced by the first successful crop <br /> grown on the reclaimed area. <br /> RECLAMATION TIMETABLE <br /> Acres ± <br /> Years Total Revegetation Road Undisturbed <br /> 1-3 50 . 00 44 . 30 1 .20 4 . 50 <br /> Logan County - Barkley Pit January 11, 2021 <br /> E-6 <br />