Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/28/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear sky, no wind, 65 degrees <br /> From: 7:00 To: 16:15 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Isaac Gonzalez) 1 4 Kessler Reclamation 6 9.25 <br /> AG W 1 6 <br /> Contractor Equipment No. TotHours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 4 Excavator 1 1 <br /> Loader 1 9.25 <br /> Compactor Roller 1 9.25 <br /> Haul Truck 2 9.25 <br /> Walk-behind Compactor 1 9.25 <br /> Description of Work Performed: <br /> The third lift was applied and packed in the ditch.The tester from AGW found all test sites to be <br /> up to standard. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Inspector: Isaac Gonzalez Date: 9/28/2020 <br />