Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 11/12/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, breezy, 31 -41 degrees <br /> From: 9:15 To: 15:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Sam Lowe) 1 1 Kessler Reclamation 5 8 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Mini-ex 1 2 <br /> skid steer 1 2 <br /> Loader 1 2 <br /> Haul Truck 1 2 <br /> Description of Work Performed: <br /> Installed 6" geo-web for low flow crossing. Keyed in each side, laid out two layers of Mirafi HP570 <br /> geotextile. The geoweb was anchored to the ground with #4 rebars spaced every three feet. <br /> The rebar was capped with the specialized rebar clip. Rebar near the road's wheel path was driven <br /> 3 inches below grade and the clip was placed at mid-level of the geoweb. <br /> Gravel (1.5") was filled in Geoweb on road surface but not yet on the key-in. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Tomorrow crew will work on the key-in portion of the geoweb. The remaining gravel will be placed <br /> in the center of the key-in first. <br /> The low-flow crossing will also received a 1" layer of 3/8" gravel as a wear surface on top of 1.5" rock. <br /> Inspector: Sam Lowe Date: 11/12/2020 <br />