Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 11/10/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Snowy, 30 degrees <br /> From: 11:00 To: 12:00 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. <br /> Hours (by Labor Class) No. <br /> Hours <br /> Oversight (Evan Valencia) 1 1 Kessler Reclamation 5 4 <br /> Contractor Equipment No. TotHours Subcontractor Equipment No. HouTotrs <br /> Passenger truck 1 1 Excavator 1 4 <br /> Grizzly 1 4 <br /> Loader 1 4 <br /> Haul Truck 1 4 <br /> Description of Work Performed: <br /> Work on riprap basin began. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences,etc.) <br /> Cold, wind and snow slowed the pace of work. <br /> Inspector: Evan Valencia Date: 11/10/2020 <br />