Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 11/6/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, 70 degrees <br /> From: 13:00 To: 14:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Evan Valencia) 1 1.5 Kessler Reclamation 5 6 <br /> Contractor Equipment No. TotHouaI Subcontractor Equipment No. HouTotrs <br /> Passenger truck 1 1 Excavator 1 6 <br /> Grizzly 1 6 <br /> Loader 1 6 <br /> Haul Truck 1 6 <br /> Description of Work Performed: <br /> The road grading was finished. <br /> Two bollards were poured for the 18" creek bypass line. <br /> 6" Geoweb delivered for road crossing. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> 3 CY load of concrete delivered for the bollard. <br /> Inspector: Evan Valencia Date: 11/6/2020 <br />