Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 11/2/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Sunny, 70 degrees <br /> From: 13:00 To: 14:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Evan Valencia) 1 1.5 Kessler Reclamation 5 8 <br /> Contractor Equipment No. Total Subcontractor Equipment No. Total <br /> Hours Hours <br /> Passenger truck 1 1 Excavator 1 8 <br /> Grizzly 1 8 <br /> Loader 1 8 <br /> Haul Truck 1 8 <br /> Description of Work Performed: <br /> Screening material at the 00 for backfilling along channel alignment continues. <br /> Backfilling the sides of the channel continues. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> Need to order gravel for both below riprap and for the low-flow crossing. <br /> Inspector: Evan Valencia Date: 11/2/2020 <br />