Daily Construction Inspection Report <br /> Project: TR-28 North Waste Rock Pile Diversion Channel Date: 9/3/2020 <br /> Contractor: Ensero Solutions <br /> Shift Hours Worked Weather: Clear, 75 degrees <br /> From: 14:30 To: 15:30 <br /> Contractor Manpower Total Subcontractor Manpower Total <br /> (by Labor Class) No. Hours (by Labor Class) No Hours <br /> Oversight (Evan Valencia) 1 1 Kessler Reclamation 6 8 <br /> Contractor Equipment No. Totl Hours Subcontractor Equipment No. TotHours <br /> Passenger truck 1 1 Excavator 1 8 <br /> Haul truck 2 8 <br /> Loader 1 2 <br /> Skid Steer 2 8 <br /> Description of Work Performed: <br /> Kessler Reclamation completed excavation of the channel/ road to the base of the NWRP. <br /> The crew is ready to begin hauling in subgrade, compacting and grading the road. <br /> Remarks by Contractor(Delays, Interruptions, Deviations, Extra Work Activities, Unusual Occurrences, etc.) <br /> Kessler's will repair their water truck for operation next week to resume work <br /> Inspector: Evan Valencia Date: 9/3/2020 <br />