Newmont Goldcorp-Cripple Creek&Victor Gold Mine <br /> Technical Specification No.03300 CAST IN PLACE CONCRETE ■ <br /> VLF2 Phase 3 <br /> Project No 475.0106 033 <br /> December S,2019 <br /> C. Standard compression tests shall be performed to determine the compressive strength: <br /> one at seven (7) days, one at fourteen (14) days, and one at twenty-eight (28) days.The <br /> fourth cylinder shall be kept in reserve for additional testing, if necessary. <br /> D. Slump testing shall be performed at the time the cylinders are prepared. <br /> Page 5 <br />