Project: Pikeview Quarry <br /> Date: Dec-2019 <br /> Table L-1 <br /> PIKEVIEW QUARRY RECLAMATION BOND SUMMARY SHEET <br /> 2019 Estimate <br /> 1 Total Facility and Structure Removal Costs $ 35,284 <br /> 2 Total Earthmoving Costs $6,335,584 <br /> 3 Total Revegetation Costs $ 408,090 <br /> 4 Total Blast and Other Reclamation Activities Costs $ 344,819 <br /> 5 Subtotal: Total Direct Costs $ 7,123,776 <br /> 6 Mobilization and Demobilization (at 1.0% of Item 5) 1.0% $ 71,238 <br /> 7 Private Contract Overhead 18.5% $ 1,317,899 <br /> 8 MLRF Administrative Costs 5.0% $ 356,189 <br /> GRAND TOTAL BOND AMOUNT $ 8,869,101 <br /> (Sum of Items 5 through 10) <br />