Laserfiche WebLink
J&T Consulting, Inc. Prowers Aggregate Operators LLC <br /> West Farts Pit <br /> 1/23/2019 <br /> FReclamation Bond Quantities and Costs <br /> Consulting.Inc. <br /> Mon-Mining Areas <br /> lReclamation Operation Quantity Unit Unit Cost Cost <br /> West Wash Plant and Sediment Pond Area <br /> Backfill Sediment Ponds 6,145 cyd $3.00 $18,435 <br /> Scarifying Ground in Disturbed Area 8.87 ac $322 $2,852 <br /> Topsoil Placement in Disturbed Area 8.87 ac $2,541 $22,539 <br /> Revegetate Disturbed Area 8.87 ac $1,100 $9,760 <br /> Scale House and Land West of Scale House <br /> Scarifying Ground in Disturbed Area 2676 ac $322 $8,605 <br /> Topsoil Placement in Disturbed Area 2676 ac $2,541 $67,998 <br /> Revegetate Disturbed Area 26.76 ac $1,100 $29,445 <br /> South Stockpile Area <br /> Scarify Ground in Disturbed Area 11.56 ac $322 $3,717 <br /> Topsoil Disturbed Area 11.56 ac $2,541 $29,374 <br /> Revegetate Disturbed Area 11.56 ac $1,100 $12,720 <br /> Parcel Area <br /> Scarifying Ground in Disturbed Area 23.05 ac $322 $7,412 <br /> Topsoil Placement in Disturbed Area 23.05 ac $2,541 $58,571 <br /> Revegetate Disturbed Area 23.05 ac $1,100 $25,362 <br /> Stockpile And Sediment Pond Area(Surface only in Phase 13) <br /> Backfill Sediment Ponds 17,655 cyd $3.00 $52,965 <br /> Scarifying Ground in Disturbed Area 14.49 ac $322 $4,659 <br /> Topsoil Placement in Disturbed Area 14.49 ac $2,541 $36,820 <br /> Revegetate Disturbed Area 14.49 ac $1,100 $15,944 <br /> Stockpile Areas(Surface only in Phase 14) <br /> Scarifying Ground in Disturbed Area 14.95 ac $322 $4,807 <br /> Topsoil Placement in Disturbed Area 14.95 ac $2,541 $37,988 <br /> Revegetate Disturbed Area 14.95 ac $1,100 $16,450 <br /> Stockpile Areas(Surface only in Phase 15) <br /> Scarifying Ground in Disturbed Area 12.11 ac $322 $3,894 <br /> Topsoil Placement in Disturbed Area 12.11 ac $2,541 $30,772 <br /> Revegetate Disturbed Area 12.11 ac $1,100 $13,325 <br /> Stockpile Areas(Surface only in Phase 16) <br /> Scarifying Ground in Disturbed Area 12.08 ac $322 $3,884 <br /> Topsoil Placement in Disturbed Area 12.08 ac $2,541 $30,696 <br /> Revegetate Disturbed Area 12.08 ac $1,100 $13,292 <br /> Stockpile Areas(Surface only in Phase 17) <br /> Scarifying Ground in Disturbed Area 15.19 ac $322 $4,884 <br /> Topsoil Placement in Disturbed Area 15.19 ac $2,541 $38,598 <br /> Revegetate Disturbed Area 15.19 ac $1,100 $16,714 <br /> Slurry Walls Constructed Around North Mining Area <br /> 20%Cost of Slurry Wall on West/East of Phases 1-3(70'avg Depth) 2,725 If $79 $216,311 <br /> 20%Cost of Slurry Wall on Outside of Phases 5-7,9,10-12(60'avg Depth) 6,625 If $68 $450,765 <br /> Mobilization 1.00 Is $13,592 $13,592 <br /> Total Direct Cost $1,303,148 <br /> Overhead and Profit Cost(13.07%) $170,321 <br /> Contract Cost $1,473,470 <br /> Project Management(7.00%) $91,220 <br /> Financial Warranty Required For Non-Mining Areas $1,564,690 <br /> Phases 1.4(11.36+10.18+10.67+9.60=41.81 acres)(Slurry wall has been constructed and leak test approved by State) <br /> ec amation Operation Quantity Unit Unit Cost Cost <br /> Topsoil Area Above Water Required for Phases 1-4 5.01 ac $2,541 $12,726 <br /> Revegetate Area Above Water Required for Phases 1-4 5.01 ac $1,100 $5,511 <br /> Total Direct Cost $18,237 <br /> Overhead and Profit Cost(13 07%) $2,384 <br /> Contract Cost $20,620 <br /> Project Management(7.00%) $1,277 <br /> Financial Warranty Required For Phases 1-4 $21,897 <br /> 2 of 3 <br />