Deep Cut LLC- 22 West Pit Page 4 <br /> Adequacy response 02 Permit # M-2017-032 <br /> I have corrected this throughout the text so it is consistent with the timetable. You may <br /> notice,that some of the numbers have changed. When I went back and started measuring <br /> and checking numbers I found they did not match the areas shown on the map and balance <br /> to the 38.35 acre total permit area. I added a small section of text explaining Options 1 & <br /> 2 before the Mining Plan Timetable to help clarify what I tried to propose in the first <br /> adequacy response. A set of pages showing the changed areas highlighted yellow is <br /> included and I supplied complete copies of Exhibit b - Mining Plan and Exhibit E - <br /> Reclamation Plan packets for the file. <br /> Exhibit E—Reclamation Plan (Rule 6.4.5): <br /> 5) The revised reclamation plan states that for Option 1, the excavated shorelines will not be <br /> retopsoiled as no topsoil will be available on site if the pre-law area to the northeast will <br /> not be redisturbed. The plan also indicates the shorelines will not be revegetated. The <br /> Applicant proposes reclaiming new shorelines by sloping and grading only. <br /> Please be advised, while other disturbed areas, such as the plant site, could remain for <br /> industrial use without retopsoiling and revegetating, all pond shorelines shall either be <br /> retopsoiled and revegetated or stabilized with riprap or other means. <br /> Please revise the reclamation plan to include one of the above mentioned options for <br /> reclamation of pond shorelines, and remove any language indicating shorelines will not <br /> be reclaimed beyond sloping requirements. Please indicate the estimated volume of <br /> material (topsoil or riprap)to be used for reclamation, the anticipated source for the <br /> material (generated on site or imported), and the haul/push distance (if generated on site) <br /> or approximate travel distance between the source and the mine site (if to be imported). <br /> It has been decided that to be consistent with the proposed Reclamation Plan, any areas <br /> above water along where mining takes placed will be resoiled using an average of 6 inches <br /> of growth medium and seeded for a distance of 25 feet from the water line or to the <br /> permit line which ever is greater. A 3.82 acres area on the southern side of the old Plant <br /> Site will be graded and left as industrial area. The roads shown on the Reclamation Plan <br /> Maps will remain after reclamation to provide landowner access around the lake. <br /> For Option 1 this means that 4.03 acres ± will be resoiled and seeded needing <br /> approximately 3,300 cubic yards of growth medium. For Option 2 the area needing resoil <br /> and seeding is 2.24 acres ± and 1,800 cubic yards ± will be needed. There is adequate <br /> growth medium on the mine area so none will need to be imported. For both options, areas <br /> needing resoiling will be graded, shaped and resoiled once they will not be disturbed again <br /> by mining so that no more then 350 feet of mining face sloping, and 0.50 acres of resoiling <br /> and seeding would be required. As noted in the Reclamation Plan, growth medium will be <br />