Laserfiche WebLink
2. Mining Timetable <br />The following timetable is a best estimate of the sequence of operations for the life of the mine <br />after May 2005 and is based on mining and selling 90,000 ftons of total product per year (this is <br />less than the maximum rate of 378,750 tons/yr but is an expected average): <br />Table D-1 Mining Timetable <br />Pit <br />Mining Time <br />Material Quantity <br />1 <br />9.1 <br />Years <br />823,000 <br />Tons <br />2 <br />23.3 <br />Years <br />2,100,000 <br />Tons <br />3 <br />6.4 <br />Years <br />577,000 <br />Tons <br />Total <br />38.8 <br />Years <br />3,500,000 <br />Tons <br />The mining schedule is planned to minimize disturbance by reclaiming areas as additional <br />mining is undertaken. Note: If large contracts are awarded to the site, production could increase <br />to the permit maximum, thereby curtailing the life of the pit. On the other hand, if contracts are <br />less than anticipated, the life of the pit could be extended. This table is based on a reasonable <br />projection of average production rates. <br />3. Mine Facilities and Operation <br />The site will contain the following facilities, it is noted where applicable whether or not the facility <br />is portable and whether it will have any fuel storage associated with it. A summary of equipment <br />and related tanks is shown below. <br />- A portable asphalt plant with associated tanks <br />- A concrete plant with associated tanks <br />- Truck scales <br />- Mine office <br />- A portable crusher with associated tanks <br />- A portable wash plant with associated tanks <br />The following list is the best estimate as to the equipment which will be used onsite throughout <br />the mine life: <br />Tri County Pit Sept 2016 D-4 <br />