Laserfiche WebLink
September 8, 2016 C-1982-056/Foidel Creek Mine JLE <br /> <br /> <br />Number of Partial Inspection this Fiscal Year: 2 <br />Number of Complete Inspections this Fiscal Year: 1 <br /> <br /> Page 6 of 11 <br /> <br /> Figure 6. Thickener Underflow Borehole and pipeline Corridor. <br /> <br />GENERAL MINE PLAN COMPLIANCE: <br />TC has almost completed the installation of the additional pipeline from the 10RT to the borehole north of the <br />Barricade Chamber. Crews were working on both ends of the line tying into the currently installed system. The <br />majority of the pipeline corridor has been backfilled, graded and topsoiled. According to Mr. Watterson, TC has <br />prepared a list of areas to be seeded this fall and the pipeline corridor will be among these areas. The corridor <br />appears stable. <br /> Figure 7. Tying into Current Water System near the 10RT Borehole end.