Laserfiche WebLink
CRIPPLE CREEK & VICTOR GOLD MINE <br />NEWMONT MINING CO. <br />SQUAW GULCH VLF WEEKLY REPORT <br />amec <br />foster <br />wheeler <br />Confirmatory Drilling: <br />UG #6520: Sandvik 700 — 13.5 hours, 1000LF. Further remediation required. <br />UG #6692: Sandvik 800 — 8.0 hours, 400LF. Further remediation required. <br />Remediation: <br />UG #6694: Began investigating unknown working. Adits found extending North/South. <br />Further remediation required. T&M = Cat excavator, 5.5 hours. <br />Underdrain System: <br />Primary Underdrain: Complete. <br />Secondary Underdrain: None. <br />Tertiary Underdrain: None. <br />Leak Detection: <br />A Cat excavator prepared leak detection trench between stations 128+00 to 130+00. A Cat <br />skidsteer assisted with construction of approximately 250 LF of leak detection per project plans <br />and specifications. <br />Geomembrane: <br />None. <br />Miscellaneous: <br />None. <br />II) Storm Water Management <br />Best Management Practices (BMPs) continued to be performed. <br />