Cripple Creek & Victor Gold Mining Company <br />Squaw Gulch VLF Phase 1 <br />(9,550-foot Elevation Bench to Geomembrane Panel P1635) <br />Final Report <br />Quality Assurance Monitoring & Test Results <br />January 2016 <br />Project No.: 74201125N0 Page 5 <br />• Review and approval of manufacturer and third party conformance certificates <br />• Observation of geotextile installation <br />• Observation and documentation of geomembrane installation <br />• Observation and documentation of trial welds <br />• Observation and documentation of defects and repairs <br />• Observation and documentation of destructive and non-destructive testing <br />1.3 Project Coordination <br />CQC and CQA activities were directed by the Amec Foster Wheeler Project Resident. <br />The Project Resident for the construction of the Project was Mr. Robert Redd. The <br />Project Manager, Ms. Andrea Meduna, PE, or Senior Geotechnical Engineer Brett Byler, <br />PE, made periodic site visits to resolve technical issues and to review Amec Foster <br />Wheeler activities. Appendix C presents a summary of the Amec Foster Wheeler staff <br />on-site during the construction period. <br />Representatives of CC&V, Ames, ECA, and Amec Foster Wheeler conducted pre- <br />construction, daily, and weekly coordination meetings throughout the construction <br />period. <br /> Daily Construction Summary Reports <br />Amec Foster Wheeler prepared daily construction summary reports as well as <br />photographic documentation (Appendix B) throughout the project to document the key <br />elements of construction and the CQA activities. On-site CQA personnel and the Project <br />Manager discussed construction activities on a regular basis; in addition, field personnel <br />prepared daily observation reports. Amec Foster Wheeler submitted these daily <br />summary reports to CC&V. Daily reports are not included in this report, but were <br />available for the Colorado Division of Reclamation, Mining and Safety (DRMS) review <br />during the course of the project. <br /> Weekly Construction Summary Reports <br />Amec Foster Wheeler prepared weekly construction summary reports which were <br />submitted to CC&V and to the DRMS. Weekly reports from the end of September <br />through mid-December 2015 are presented in Appendix D. Weekly construction <br />summary reports are continued from the Squaw Gulch VLF Phase 1 (9,450’ to 9,550’ <br />Bench) report by Amec Foster Wheeler.