that the operation will mine and sell 100,000 tons of total product per year, on an average. The time- <br />table in the mining plan also reflects these rates. The expected reclamation timetable is given below: <br />RECLAMATION TIMETABLE <br />Task <br /># <br />Description <br />Time Needed <br />months <br />1 <br />Reclaim mining area east of existing Berry Pit (before final reclam) <br />0.5 <br />2 <br />For Strips 2,3,4,5,6,7,8,9 move soil and overburden to reclaim previ- <br />ous strips. Ongoing reseeding and mulching of these strips. <br />160 <br />3 <br />Backfill overburden and soil in Strip 9 from stockpiles in old pit area. <br />0.25 <br />4 <br />Move all portable equipment offsite <br />0.1 <br />4 <br />Regrade pit area and stockpile area <br />0.5 <br />5 <br />Retopsoil processing area and stockpile area. <br />0.25 <br />6 <br />Regrade protection berm and sediment pond <br />0.25 <br />7 <br />Ripping or harrowing of any needed areas <br />0.25 <br />8 <br />Reseed and mulch last 4 strips, processing area and stockpile area <br />0.2 <br />Total Time <br />162.3 <br />4. Post -Reclamation Site Drainage <br />The entire permit area will drain to the southwest after reclamation, as shown on Map F. This is the <br />original drainage direction toward the White River. <br />Berry Pit 3/02 17 <br />