Laserfiche WebLink
Al. <br /> Cripple Creek&Victor Gold Mining Company <br /> Squaw Gulch VLF Phase 1 (9,450 foot to 9.550 foot bench) amec <br /> Final Report Addendum foster <br /> Quality Assurance Monitoring&Test Results wheeler <br /> December 1. 2015 <br /> 2.1.1 Remediation of Shafts, Stopes, and Shallow Surface Pits <br /> The following is a general approach used to remediate isolated shafts and shallow <br /> surface pits (refer to figure UG1 in Appendix M.1 of the report for visual representation <br /> of the descriptions below): <br /> Open Workings: <br /> For open workings, the excavations were backfilled with CSB to approximately 10 feet <br /> below the finished surface grade. The surface of the CSB was compacted using the <br /> bucket from a Caterpillar excavator. A minimum 3-foot-thick CP was cast into the shaft <br /> and allowed to cure for a minimum of 7 days. A minimum 7-foot-thick layer of CRF was <br /> then placed onto the CP. SF was then placed to the final grade as needed. In some <br /> cases, the excavation did not require placement of CSB prior to placement of the CP <br /> and CRF. <br /> Collapsed Workings <br /> For collapsed workings, collapsed materials were excavated to a depth of 25 feet below <br /> finished grade. The excavations were either backfilled with CSB to approximately 3 feet <br /> below the soil/bedrock interface or shaped for placement of a CP. The surface of the <br /> CSB was compacted using the bucket from a Caterpillar excavator. A minimum 3-foot- <br /> thick CP was cast into the shaft and allowed to cure for 7 days. A minimum 7-foot-thick <br /> layer of CRF was then placed over the CP. After the CRF was allowed to cure, SF was <br /> then placed to the final grade as needed. <br /> Shallow Surface Pits <br /> Shallow surface pits that were less than 25 feet below the final SLF grade were <br /> excavated to bedrock or pit termination. The pits were then backfilled with compacted <br /> SSF and SF to the bottom of the SLF layer. In some cases, shallow surface pits were <br /> completely removed during slope re-contouring and required no further remediation. <br /> 2.1.2 Remediation of Lateral/I ncli nes/Ad its <br /> A number of laterals and adits were identified within the Phase 1 VLF footprint. Per the <br /> remediation recommendations, historic underground workings were identified within 50 <br /> feet of the existing grade elevation and remediated. Workings that were 50 feet or more <br /> below the final grade were not remediated. <br /> Remediation for laterals and adits consisted of drilling nominal 3-inch-diameter blast <br /> holes into the crown pillar (the rock between the ground surface and the roof of the <br /> working) using a pneumatic hammer track drill rig. The blast holes were loaded and the <br /> crown pillars blasted into the void. For some of the shallower workings, the blasted <br /> material was excavated and replaced with compacted fill. For deeper blasted laterals <br /> 8 <br />